Wednesday, May 15, 2013

The Political Nature of Program Evaluation

Program evaluation is a political process. An evaluator who ignores, avoids, or mismanages the political realities of evaluation limits the effectiveness and usefulness of the process (Fitzpatrick, Sanders, & Worthen, 2010). Ethical complexities wind in and among the more overt political features of evaluation such as financial support, stakeholder allegiance, and social impact. Morris and Cohn (1993) detail several ways in which stakeholders may seek to influence evaluation outcomes, and Fitzpatrick et al. (2010) caution that evaluators also need to be aware of their own potential to taint the evaluative process.

If we accept that evaluation is political (and, therefore, ripe for ethical complication), then we must ask how best to balance the objectivity required in a program evaluation with the political interests of stakeholders. We must ask, “What ethical standards and values need to be emphasized in program evaluation?”

The American Evaluation Association’s (AEA) Program Evaluation Standards (Yarbrough, Shulha, Hopson, & Caruthers, 2011) and Guiding Principles for Evaluators (American Evaluation Association, 2004) provide a broad, somewhat obvious, framework for ethical conduct.

Fitzpatrick et al. (2010) are more specific, encouraging evaluators to be both self-reflective about their role in the evaluation process and circumspect about client requests, so as to minimize the potential for bias and ethical compromise: “…the client may be asking for what the client perceives as editing changes, but the evaluator sees as watering down the clarity or strength of the judgments made” (p. 81). And Schweigert (2007) roots evaluator responsibility in the notion of justice – public, procedural, and distributive.

From this we can extract answers to the question “What ethical standards and values need to be emphasized in program evaluation?” 

Ethical standards:
  • Those detailed in the AEA’s and other professionally recognized codes of conduct.

Values:
  • Commitment to truth – what Schweigert (2007) calls the priority of justice
  • Cultural sensitivity
  • Respect (for stakeholders, ourselves, and the evaluation process)

It seems that no professional code nor personal charter can do the whole job. No matter how pointed the professional standards, situational circumstance requires evaluators to make interpretations and best guesses (Schweigert, 2007), which are subject to bias and ethical compromise, as Weiss (2006) lays bare any illusions we may have that we are above or beyond the snare of bias and ethical confusion: “You never start from scratch. We pick up the ideas that are congenial to our own perspective. Therefore, people pick up this thought or that interpretation of a research report that fits with what they know or what they want to do” (p. 480).

I have thought about this a lot over the past few days, returning again and again to Sieber’s (1980) conclusion that “being ethical in program evaluation is a process of growth in understanding, perception, and creative problem-solving ability that respects the interests of individuals and of society” (p. 53). 


References
 
American Evaluation Association, 2004. Guiding principles. Retrieved from www.eval.org/Publications/Guiding Principles.asp.

Fitzpatrick, J., Sanders, J., & Worthen, B. (2010). Program evaluation: Alternative approaches and practical guidelines (4th ed.). Boston, MA: Pearson

Morris, M., & Cohn, R. (1993). Program evaluators and ethical challenges: A national survey. Evaluation Review, 17, 621-642.

Schweigert, F. J. (2007). The priority of justice: A framework approach to ethics in program evaluation. Evaluation and Program Planning, 30(4), 394–399.

Sieber, J. E. (1980). Being ethical: Professional and personal decisions in program evaluation. In R.E. Perloff & E. Perloff (Eds.), Values, ethics, and standards in evaluation. New Directions for Program Evaluation, No. 7, 51-61. San Francisco: Jossey-Bass. 

Weiss, C. H., & Mark, M. M. (2006). The oral history of evaluation Part IV: The professional evolution of Carol Weiss. American Journal of Evaluation, 27(4), p. 474-483.

Thursday, May 2, 2013

Fostering Behavior Change

In Fostering Behavior Change (Tulgan, 2013), Bruce Tulgan offers seven best practices for creating training that increases knowledge uptake and meaningful behavior change. Two-thirds of my way through a Master’s degree in Instructional Design and Technology, I first thought Tulgan’s tips were obvious. Simplistic. After thinking about it quite a bit, I’m sure they are. Why would Tulgan, an established training expert, tell us what we already know? Because it’s true. Because he’s right.  

There is no magic to training, and all the cool whiz-bang technology in the world doesn’t change the fact that effective training is a product of sound design and delivery. Tulgan’s tips should seem obvious, because he is reminding instructional designers and trainers of what we already know, yet sometimes fail to execute. We need to leverage needs assessments to align instructional objectives with identifiable skill and knowledge gaps, link instructional content to real-life, and deliver content to multiple memory centers. Sticky training offers actionable solutions and learning extensions. Finally, we need to follow up and cultivate support for ongoing learning.

We know this. We need to do it. Every time.

Make a great day,


Reference
 
Tulgan, B. (2013, January/February). Fostering behavior change. Training, 50(1), p. 9.

Sunday, April 21, 2013

The Future of Distance Learning

I was recently asked to share my thoughts on the future of distance learning, and I’m struggling to be original about the topic. It seems self-evident that the future of distance learning is expansive and inclusive and ever-so-much-more-so. Distance learning has burgeoned far beyond the realm of training for medical transcription and is ubiquitous in corporate settings, higher education, and K-12 education. But the real driver is not just that more people are learning at a distance; it’s that more people are recognizing distance education as a viable alternative to traditional F2F learning. The quality of distance learning coupled with the broad availability of emerging technologies have transformed distance learning from a fall-back, Plan B position to a deliberate first choice.

The growing acceptance of distance learning is fueled by a global increase in online communication. As more of us spend more time together online, engaging with more diverse groups than we ever would in person, the complications of distance matter less, and the benefits matter more, to individuals, corporations, and educational institutions (Laureate Education, Inc., 2009).

If there is a popularity ceiling for distance learning, it may be framed and fortified by distance education institutes themselves. A study by Gambescia and Paolucci (2009) found that few institutions effectively leverage their academic integrity in their promotions, relying instead on convenience and flexibility to appeal to potential students. The study didn’t reveal reasons for this, but I’ll speculate on two reasons:

  1. Convenience and flexibility are big draws for distance learning. It’s slam dunk marketing.
  2. It’s easier to leverage innate characteristics of distance learning than it is to ensure the academic integrity of distance education.
As Gambescia and Paolucci note, “to ensure a high-level of academic fidelity and integrity for online degree programs is not simply a matter of the university transferring current academic assets to the new online degree programs—throwing it over the fence, so to speak. Transferring such academic assets to online degree programs will understandably call for changes, as the inputs and outputs of online degree program offerings by design can be quite different” (Gambescia & Paolucci, 2009).

Assuming the momentum gathering around distance learning is indeed forward momentum, distance learning institutions themselves have work to do. Enrollment – ballooning. Acceptance – growing. Perceived quality – ?

More is expected of those to whom more has been given; so it is in distance learning as in other aspects of life. Those of us who are distance learners or work in distance learning are uniquely positioned to cultivate positive impressions of distance learning. We do this best by doing well in our endeavors and demonstrating the high standards of distance education today.

Sally Bacchetta

References

Gambescia, S., & Paolucci, R. (2009). Academic fidelity and integrity as attributes of university online degree program offerings. Online Journal of Distance Learning Administration, 12(1). Retrieved from http://www.westga.edu/~distance/ojdla/spring121/gambescia121.html

Laureate Education, Inc. (Producer). (2010). The future of distance education [DVD]. Baltimore, MD: Author

Schmidt, E., & Gallegos, A. (2001). Distance learning: Issues and concerns of distance learners. Journal of Industrial Technology, 17(3). Retrieved from http://atmae.org/jit/Articles/schmidt041801.pdf

Wednesday, April 10, 2013

Scope Creep: A Horror Story

This week brings another interesting assignment for my Project Management course. I am asked to reflect on an experience I had with scope creep and, well... see for yourself. 

Describe a project, either personal or professional, that experienced issues related to scope creep.  In a former career I managed a residential treatment program for adults with mental illnesses. I supervised the staff and residents of a ten-apartment facility, provided counseling, assisted with activities of daily living, and participated in inter-disciplinary planning and treatment for each resident. The need for mental health care far outpaced available resources, and the CEO continually scouted for new properties to acquire and convert to accommodate our long waiting list.

Such a property was found not far from my facility, and I was flattered when the CEO asked for my help in establishing the new facility. He explained that I would maintain my current duties and also be responsible for interviewing, hiring, and training the new staff. I would also supervise them until a manager was hired and trained. I had a good deal of experience and a solid team, and I was confident that I could take over the additional responsibilities without compromising either program.

What specific scope creep issues occurred?  Almost immediately my role at the new location changed from temporary manager to design consultant-construction site supervisor-accounting rep-professional cleaner-building superintendent. With each passing day I found myself making decisions I had neither the qualifications nor the desire to make.

What interior paint colors do you want? Sally can decide.
We need to order furniture. Let’s ask Sally to do it.
What equipment do we need to set up the new office? The new kitchen? The residents’ bedrooms? Have Sally develop a list. Give Sally the corporate credit card. Let’s have Sally be there to take delivery.
There are bats in the fireplace. My invoice hasn’t been paid. We found mold in the basement. The porch foundation didn’t pass inspection. Call Sally!

How did you or other stakeholders deal with those issues at the time?  My staff stepped up and took on extra responsibilities. The contractors became progressively less motivated, less patient, and less concerned with quality. The CEO went on a 14-day cruise with his wife, and I quit exercising, dusting, and cooking decent meals; I drank too much coffee and slept very little, always with a pager by my side.

Looking back on the experience now, had you been in the position of managing the project, what could you have done to better manage these issues and control the scope of the project? What I could have done better is to actually manage the project instead of scrambling to keep up with the scope creep. I lacked project management experience, and I was so focused on the overwhelming need for more formalized mental health support that it didn’t occur to me to refuse (or question) any of the tasks that were dumped on me.

If I knew then what I know now, I would have drafted some type of work breakdown structure (Portny, Mantel, Meredith, Shafer, Sutton, & Kramer, 2008). I would have listed Level 1, 2, 3, etc., tasks and sub-tasks and identified and allocated resources for each. I would have outlined an appropriate chain-of-command and sought approval for each of these documents (Greer, 2010). And I would have said “no.”

“No” to hauling office furniture up a flight of stairs. “No” to manually seeding the acre lot using an old rusty spreader so we could save a few bucks. And absolutely, positively, “no” to checking to see if there really were bats in the fireplace. Yeah, there were. There sure were.


Resources
 
Greer, M. (2010). The project management minimalist: Just enough PM to rock your projects! (Laureate custom ed.). Baltimore: Laureate Education, Inc.

Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E. (2008). Project management: Planning, scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons, Inc.

Wednesday, March 27, 2013

Managing Your Project Schedule

One of the most challenging aspects of instructional design project management is managing the project schedule. The schedule must be rigid enough to provide structure, yet fluid enough to allow for the inevitable inevitabilities of project work. One way to develop your own scheduling style is to read and learn about what works for other people, so here is my two cents.

As often as possible I work back-to-front to draft my ideal network diagram, beginning with the end date of the final deliverable and working backwards to identify prerequisite (predecessor) activities and deliverables, time requirements, and event deadlines, based on required, procedural, and logical relationships (Portny et al., 2008).

I then compare my ideal network diagram to what I call “probable reality,” which is a consideration of my experience with:

  • Projects in general
  • Similar projects
  • What I know about this client
  • What I know about this project team
  • My own schedule and workload

Probable reality reflects my best guess of project limitations and unknowns (Portny et al., 2008) and their anticipated impact on the project. For example, let’s assume that my project team has 21 days to submit a deliverable of a module outline with instructional objectives. I consider my experience with projects in general and similar projects, and determine that I need 14 days (span time) to complete the deliverable.

In my ideal network diagram I allow 3 days for the client to review and approve the outline (17 days). However, I know this client is slow to review and approve materials, so I build an extra 2 days into the activity phase (19 days). That leaves the team only 2 days to review client feedback, make revisions, and re-submit the outline to the client.

If I know the project team is highly organized and on point, I may take a risk and go with that. But if I don’t know the project team well, or if I know them to be slow or unorganized or very busy, I will decide that it’s not enough time and I need to cut some time somewhere else in the process.

Every activity eats up time (Laureate Education, Inc., 2012), and when time is tight, my first choice is to cut time on my end where I have the most control. I then consider my schedule and workload to find a way to complete the deliverable in less than 14 days.

Freelance work can be very patchwork, and I sometimes function as ID, writer, and PM all in one. In those situations I can track everything with a simple Word document and an Excel spreadsheet. When working with a team, however, project management software is almost essential (Fabac, 2006). It facilitates consistent communication and sharing of timelines, milestones, progress, and changes between team members and clients.

Project work is a wild ride every time. It can be stressful, but the feeling of success is a rush!

Sally Bacchetta

References

Fabac, J. N. (2006). Project management for systematic training. Advances in Developing
Human Resources, 8(4), 540–547.

Laureate Education, Inc., (Producer). (2012). Creating a project schedule. [Multimedia Program]. Baltimore, MD: Author.

Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E.
(2008). Project management: Planning, scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons, Inc.

Thursday, March 21, 2013

Communication

Which mode of communication do you prefer: written, audio, or video? This week I reviewed a sample communication in each of those three modes to see if the type of communication affected my interpretation of the message. Here is the communication in written form: 

“Hi Mark,
I know you have been busy and possibly in that all day meeting today, but I really need an ETA on the missing report. Because your report contains data I need to finish my report, I might miss my own deadline if I don’t get your report soon. Please let me know when you think you can get your report sent over to me, or even if you can send the data I need in a separate email.
I really appreciate your help.
Jane” (Laureate Education, Inc., 2012).

Written – When I read this I experienced Jane as feeling urgent, conscientious, and compassionate. She is clear about her request and also steps outside her own perspective to share insight into Mark’s workload and offer a compromise solution. If I got this email I would make it a priority to give Jane what she needs and thank her for her patience.

Audio – Next, I listened to an audio recording of Jane reading the same communication. Again, Jane came across as urgent, conscientious, and compassionate, although slightly less assertive.

Video – Finally, I watched a video of Jane speaking the communication. Jane seemed friendly, supportive, and quite a bit less assertive in the email and audio. Jane did something that women often do (and it drives me crazy!), which is to make a statement sound like a question by raising her voice inflection at the end of the sentence. “So please let me know…? If you can send it over soon?” (Laureate Education, Inc., 2012). This diminishes the urgency of the situation and suggests that she is flexible about waiting for the data. “According to Deborah Tannen, we hear a downward cadence as ‘closed’ or ‘final,’ with the extreme being ‘controlling.’ Conversely, we hear an upward cadence as ‘open’ and ‘flexible’ with the extreme being ‘indecisive’” (Tannen, 2011).If I were an over-scheduled Mark, I would not likely prioritize getting Jane’s data to her.

After this exercise I reflected on the nature of communication among some of the project teams I’ve worked with. All have blended written, audio and face-to-face communication. Is one mode better than another?

I prefer written communication, and I want it to be clear and concise. (Ernest Hemingway never wasted a word, and I wish more people were that way.) Some people need to give chapter and verse of everything they say, and others like to chit chat for a minute or two before they discuss the issue at hand.

A project manager needs to be able to reach and receive from everyone on the team, regardless of their communication style. This is easier when the PM is familiar with the team. Once I recognize someone’s style I make an effort to communicate with them in that style and mode. It helps ensure that the message sent is actually received.



References

Laureate Education, Inc., (Producer). (2012). The Art of Effective Communication. [Multimedia Program]. Baltimore, MD: Author.
 
Tannen, D. (2011). The eloquent woman blog. Retrieved from http://eloquentwoman.blogspot.com/2011/09/do-you-end-sentences-with-upward.html

Thursday, March 14, 2013

Sales Training Project Post-mortem



The project debrief, or post-mortem, is one of my favorite parts of a project because I learn as much from a negative project experience as I do from a positive one. By identifying what did and didn’t work I can be better prepared for the next project (Greer, 2010). This is my analysis of the “Rep Expo” training project.
Context
I was hired to design the instruction and develop the content for a three day sales training workshop. Each module was to be designed as a stand-alone unit to be delivered by a face-to-face facilitator. The client provided a list of topics to be addressed, and I was given the freedom to make all design and content decisions, with draft materials to be approved by the project manager and the client. The PM described the client as “extremely picky, unavailable, and unable to articulate what he wants.” I was brought in (freelance) because two in-house individuals had failed to successfully complete the project. The project was now well behind timeline and over budget, and the client had threatened to terminate the contract “if you folks can’t turn this around quickly.” We were given 60 days to complete the project and a successful beta test.

Post-mortem
What contributed to the project’s success or failure? The positive and negative drivers of this project were closely enmeshed. What follows is my pro and con post-mortem list of PM actions that drove the project to failure.

 Pro: Arranged for a F2F kickoff meeting with the client to clarify client objectives, expectations, and other project details.
Con: Attended the meeting with several other internal team members and behaved unprofessionally (holding whispered personal conversations while the client was talking, openly disagreeing with the client about details of the project, frequently checking her watch, leaving to make personal phone calls, and assuring the client that we had the capabilities to develop specific learning objects knowing full well that we did not).

Pro: Developed and maintained a comprehensive production schedule.
Con: Made no attempt to adhere to the schedule; it was completely moot.

Pro: Scheduled weekly internal meetings.
Con: Rescheduled or canceled most meetings with little advance notice; was absent from several meetings; meeting minutes routinely contained significant errors.  

Pro: Supplied me with contact information for client-selected SME.
Con: Failed to notify SME that he had been selected to consult on the project, so my initial call was a complete surprise. Failed to include SME in internal meetings and progress reports.

Pro: Provided me with a written SOW and contract for my services.
Con: Ignored the terms of payment detailed in the contract.

Pro: Assigned a team of graphic designers, animators, programmers, and editors to support my piece of the project.
Con: Failed to monitor their progress or hold them accountable to any standards, which resulted in loss of time and excessive costs.

Which parts of the PM process, if included, would have made the project more successful? Why?
  1. Project planning (Portny, Mantel, Meredith, Shafer, & Sutton, 2008). If the PM had developed a clear and feasible project plan and held team members accountable, we would have been able to meet our deadlines.
  2. Reporting on project activities (Portny et al., 2008). The PM routinely “hid” from the client and other team members, waiting several days to return time sensitive calls and emails. Delayed communication resulted in missed deadlines, incomplete revisions, an unhappy client, and frustrated team members.
  3. Managing the accomplishment of objectives, within time and budget targets (Portny et al., 2008). The PM is responsible for planning, organizing, and controlling the project and the project team (Portny et al., 2008). Had she actually managed at all we may have been able to save the project and the client.
  4. Identifying tasks and phases necessary to complete the project (Greer, 2010). “Because projects are, by definition, temporary endeavors, it is essential to identify how each phase or collection of activities will be judged by stakeholders to be formally or officially completed” (Greer, 2010, p. 20). Although the PM identified the ultimate deliverables, she neglected the milestone deliverables along the way.
  5. Driving forward. The PM bears responsibility for tracking progress against objectives and intervening as necessary to “correct problems, remove obstacles, and keep the project moving as planned” (Greer, 2010, p. 31). This project became mired again and again; the client missed his schedule launch date, which caused him professional embarrassment and personal stress.

Outcome
The PM created enough of a project shell that we had some successes throughout the project, most significantly that the client was very pleased with the design, content, and interactivity of the workshop. However, his dissatisfaction with the issues detailed herein prevailed, and he terminated the contract on the basis of non-performance.  

 References
(Laureate custom ed.). Baltimore: Laureate Education, Inc. 

Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E.
(2008). Project management: Planning, scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons, Inc.